Mechanical stubbing

Start:  11-05-13

ID:   3

Finish: 11-05-19

Dur: 5 days

Res:    

Erecting fencing with wickets and gates

Start:  11-05-13

ID:   4

Finish: 11-05-16

Dur: 2 days

Res:    

Erecting gateways 

Start:  11-05-13

ID:   5

Finish: 11-05-13

Dur: 0,5 days

Res:    

Timber wickets with lath and posts, steel posts - erecting

Start:  11-05-13

ID:   6

Finish: 11-05-13

Dur: 0,5 days

Res:    

EARTHWORKS

Start:  11-05-20

ID:   7

Finish: 11-05-24

Dur: 3 days

Comp: 0%

Removal of humus with use of dozers, thickness of the layer up to 15 cm

Start:  11-05-20

ID:   8

Finish: 11-05-20

Dur: 0,5 days

Res:    

Measurement during foundation trench, terrain low-lying and plain

Start:  11-05-20

ID:   9

Finish: 11-05-20

Dur: 0,5 days

Res:    

Earthworks with push shovel with transport of excavated material by trucks, excavator 0,4m^3, soil category I-II

Start:  11-05-23

ID:   10

Finish: 11-05-24

Dur: 2 days

Res:    

FOUNDATION

Start:  11-05-25

ID:   11

Finish: 11-06-14

Dur: 14,5 days

Comp: 0%

Concrete subfloor on the subsoil, concrete delivery with use of wheel-barrow

Start:  11-05-26

ID:   13

Finish: 11-05-26

Dur: 1 day

Res:    

GROUND FLOOR

Start:  11-06-14

ID:   20

Finish: 11-07-15

Dur: 23,5 days

Comp: 0%

Floor on the soil

Start:  11-06-14

ID:   21

Finish: 11-06-29

Dur: 11,5 days

Comp: 0%

Subfloor made of compacted loose materials on the soil, sand

Start:  11-06-14

ID:   22

Finish: 11-06-17

Dur: 3 days

Res:    

Formwork assembling

Start:  11-05-25

ID:   12

Finish: 11-05-25

Dur: 1 day

Res:    

Formwork disassembling

Start:  11-06-01

ID:   14

Finish: 11-06-01

Dur: 1 day

Res:    

BUILDING SITE PREPARATION WORKS

Start:  11-05-13

ID:   2

Finish: 11-05-19

Dur: 5 days

Comp: 0%

START

Milestone Date: Fri 11-05-13

ID: 1

Walls

Start:  11-06-30

ID:   28

Finish: 11-07-15

Dur: 12 days

Comp: 0%

Page 1

background image

Stairs

Start:  11-06-30

ID:   34

Finish: 11-06-30

Dur: 0,5 days

Comp: 0%

FLOOR 

Start:  11-07-18

ID:   37

Finish: 11-08-17

Dur: 22,5 days

Comp: 0%

Slab

Start:  11-07-18

ID:   38

Finish: 11-08-01

Dur: 10,5 days

Comp: 0%

Page 2

background image

ATTIC

Start:  11-08-17

ID:   51

Finish: 11-09-02

Dur: 12,5 days

Comp: 0%

Page 3

background image

Page 4

background image

Page 5

background image

Foundation made of bricks with cement mortar

Start:  11-06-02

ID:   15

Finish: 11-06-03

Dur: 2 days

Res:    

Damp insulation, double layer of building paper

Start:  11-06-06

ID:   16

Finish: 11-06-06

Dur: 1 day

Res:    

Foundation walls made of bricks, common brick, cement mortar, thickness of 2 brick

Start:  11-06-07

ID:   17

Finish: 11-06-10

Dur: 4 days

Res:    

Damp insulation of vertical surface, bulding paper, 1 layer

Start:  11-06-13

ID:   18

Finish: 11-06-13

Dur: 1 day

Res:    

Backfilling of excavation with bulldozers, replacing on the distance up to 10 m , soil category I-II, bulldozer 74 kW (100 KM)

Start:  11-06-14

ID:   19

Finish: 11-06-14

Dur: 0,5 days

Res:    

Concrete subfloor on the soil, concrete delivery by pump

Start:  11-06-20

ID:   24

Finish: 11-06-22

Dur: 2 days

Res:    

Reinforcement of the concrete elements of the building, round ribbed steel bars, Fi 8-14 mm

Start:  11-06-22

ID:   25

Finish: 11-06-23

Dur: 1 day

Res:    

Reinforced slab, concrete delivery by pump

Start:  11-06-23

ID:   26

Finish: 11-06-23

Dur: 0,5 days

Res:    

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

Start:  11-06-30

ID:   29

Finish: 11-07-15

Dur: 12 days

Res:    

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 1-brick

Start:  11-06-30

ID:   30

Finish: 11-07-01

Dur: 1,5 days

Res:    

Posts and fillars made of common brick , dimension: 2x2 of brick, cement - lime mortar

Start:  11-06-30

ID:   31

Finish: 11-06-30

Dur: 1 day

Res:    

Lintels made by using PERI formwork, ratio perimeter/cross-section: up to 8 m/m2, version 1

Formwork assembling

Start:  11-06-17

ID:   23

Finish: 11-06-20

Dur: 1 day

Res:    

Formwork disassembling

Start:  11-06-29

ID:   27

Finish: 11-06-29

Dur: 1 day

Res:    

Page 6

background image

Start:  11-06-30

ID:   32

Finish: 11-06-30

Dur: 1 day

Res:    

Chimney ducts made of hollow bricks

Start:  11-06-30

ID:   33

Finish: 11-06-30

Dur: 0,5 days

Res:    

Buildings made of elements OWT-67N : staircase landing

Start:  11-06-30

ID:   35

Finish: 11-06-30

Dur: 0,5 days

Res:    

Buildings made of elements OWT-67N : flight of the stairs

Start:  11-06-30

ID:   36

Finish: 11-06-30

Dur: 0,5 days

Res:    

DZ type slab, hollow brick DZ-3, prefabricated beams

Start:  11-07-19

ID:   40

Finish: 11-07-22

Dur: 3,5 days

Res:    

DZ type slab, hollow brick DZ-3, prefabricated beams, monolithic ring beam in the external walls with thickness up to 30 cm

Start:  11-07-25

ID:   41

Finish: 11-07-25

Dur: 0,5 days

Res:    

Buildings made of elements OWT-65N: gravel concrete slab

Start:  11-07-19

ID:   44

Finish: 11-07-19

Dur: 0,5 days

Res:    

Walls

Start:  11-08-01

ID:   45

Finish: 11-08-17

Dur: 12 days

Comp: 0%

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

Start:  11-08-01

ID:   46

Finish: 11-08-17

Dur: 12 days

Res:    

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

Start:  11-08-01

ID:   47

Finish: 11-08-02

Dur: 1,5 days

Res:    

Posts and fillars made of common brick , dimension: 2x2 of brick, cement - lime mortar

Start:  11-08-01

ID:   48

Finish: 11-08-02

Dur: 1 day

Res:    

Lintels made by using PERI formwork, ratio perimeter/cross-section: up to 8 m/m2, version 1

Start:  11-08-01

ID:   49

Finish: 11-08-02

Dur: 1 day

Res:    

Chimney ducts made of hollow bricks

Start:  11-08-01

ID:   50

Finish: 11-08-02

Dur: 1 day

Res:    

Formwork assembling

Start:  11-07-18

ID:   39

Finish: 11-07-19

Dur: 1,5 days

Res:    

Overconcrete pouring, concrete delivery by pump

Start:  11-07-25

ID:   42

Finish: 11-07-25

Dur: 1 day

Res:    

Formwork disassembling

Start:  11-07-29

ID:   43

Finish: 11-08-01

Dur: 1,5 days

Res:    

Page 7

background image

Slab

Start:  11-08-17

ID:   52

Finish: 11-08-31

Dur: 10,5 days

Comp: 0%

DZ type slab, hollow brick DZ-3, prefabricated beams

Start:  11-08-19

ID:   54

Finish: 11-08-24

Dur: 3,5 days

Res:    

DZ type slab, hollow brick DZ-3, prefabricated beams, monolithic ring beam in the external walls with thickness 

Start:  11-08-24

ID:   55

Finish: 11-08-24

Dur: 0,5 days

Res:    

Wall beam

Start:  11-09-01

ID:   58

Finish: 11-09-02

Dur: 2 days

Comp: 0%

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

Start:  11-09-01

ID:   59

Finish: 11-09-02

Dur: 2 days

Res:    

Chimney ducts made of hollow bricks

Start:  11-09-01

ID:   60

Finish: 11-09-01

Dur: 0,5 days

Res:    

ROOF

Start:  11-09-05

ID:   61

Finish: 11-09-14

Dur: 8 days

Comp: 0%

Rafter framing

Start:  11-09-05

ID:   62

Finish: 11-09-08

Dur: 3,5 days

Comp: 0%

Collar roof with wall beam under plain tile double layered, rafter framing with span 12 m

Start:  11-09-05

ID:   63

Finish: 11-09-08

Dur: 3,5 days

Res:    

Covering

Start:  11-09-08

ID:   64

Finish: 11-09-14

Dur: 4,5 days

Comp: 0%

Damp and water-proof insulation made of wide polyethylene sheeting, horizontal insulaton uder flooring

Start:  11-09-08

ID:   65

Finish: 11-09-12

Dur: 2 days

Res:    

Thermal and acoustic insulation made of mineral wool, vertical

Start:  11-09-08

ID:   66

Finish: 11-09-09

Dur: 1,5 days

Res:    

Placing asphalt shingles with width 8 cm

Start:  11-09-08

ID:   67

Finish: 11-09-14

Dur: 4,5 days

Res:    

FINISHING WORKS

Start:  11-09-15

ID:   73

Finish: 11-10-19

Dur: 24,5 days

Comp: 0%

Partition walls

Start:  11-09-15

ID:   74

Finish: 11-09-16

Dur: 1,5 days

Comp: 0%

Woodwork

Start:  11-09-15

ID:   76

Finish: 11-09-16

Dur: 2 days

Comp: 0%

Formwork assembling

Start:  11-08-17

ID:   53

Finish: 11-08-18

Dur: 1,5 days

Res:    

Overconcrete pouring, concrete delivery by pump

Start:  11-08-24

ID:   56

Finish: 11-08-25

Dur: 1 day

Res:    

Formwork disassembling

Start:  11-08-30

ID:   57

Finish: 11-08-31

Dur: 1,5 days

Res:    

Page 8

background image

Page 9

background image

Roof gutter made of galvanized iron, semicircular with diameter 15 cm

Start:  11-09-08

ID:   68

Finish: 11-09-09

Dur: 1 day

Res:    

Downpipe  made of galvanized iron, semicircular with diameter 15 cm

Start:  11-09-08

ID:   69

Finish: 11-09-09

Dur: 1 day

Res:    

Different treatment made of galvanized iron with width up to 25 cm

Start:  11-09-08

ID:   70

Finish: 11-09-12

Dur: 2 days

Res:    

Erecting chimney bench

Start:  11-09-08

ID:   71

Finish: 11-09-08

Dur: 0,5 days

Res:    

Placing windows in the roof slope

Start:  11-09-08

ID:   72

Finish: 11-09-09

Dur: 1 day

Res:    

Ironwork

Start:  11-09-15

ID:   93

Finish: 11-09-15

Dur: 1 day

Comp: 0%

KONIEC

Milestone Date: Wed 11-10-19

ID: 105

Page 10

background image

Page 11

background image

Page 12

background image

Partition walls of the mutli-storey buildings with thickness 12 cm, made of lime - sand blocks, type: 2NFD

Start:  11-09-15

ID:   75

Finish: 11-09-16

Dur: 1,5 days

Res:    

External door frame, double painting on the building site

Start:  11-09-15

ID:   77

Finish: 11-09-15

Dur: 0,5 days

Res:    

External door leaf panel, prefabricated up to 2 m2

Start:  11-09-15

ID:   78

Finish: 11-09-15

Dur: 0,5 days

Res:    

Windows and balcony doors made of timber, composite

Start:  11-09-15

ID:   79

Finish: 11-09-16

Dur: 2 days

Res:    

Casement window, without ventilator, 0,5-0,7 m2

Start:  11-09-15

ID:   80

Finish: 11-09-15

Dur: 0,5 days

Res:    

Page 13

background image

Casement window, without ventilator, 0,7-1,0 m2

Start:  11-09-15

ID:   81

Finish: 11-09-15

Dur: 0,5 days

Res:    

Casement window, without ventilator, 1,0-1,5 m2

Start:  11-09-15

ID:   82

Finish: 11-09-16

Dur: 2 days

Res:    

Casement window, without ventilator, 1,5-2,0 m2

Start:  11-09-15

ID:   83

Finish: 11-09-16

Dur: 1,5 days

Res:    

Casement window, without ventilator, 2,0-3,0 m2

Start:  11-09-15

ID:   84

Finish: 11-09-15

Dur: 0,5 days

Res:    

Door frame with expansion slot 

Start:  11-09-15

ID:   85

Finish: 11-09-15

Dur: 1 day

Res:    

Portcullises to the garage, welded to concrete door frame

Start:  11-09-16

ID:   86

Finish: 11-09-16

Dur: 1 day

Res:    

Horizontal insulation

Start:  11-09-19

ID:   87

Finish: 11-10-03

Dur: 11 days

Comp: 0%

Damp and water-proof insulation, made of wide polyethylene sheeting, horizontal insulaton uder flooring

Start:  11-09-19

ID:   88

Finish: 11-09-22

Dur: 3,5 days

Res:    

 Horizontal thermal and acoustic insulation made of polystyrene

Start:  11-09-22

ID:   89

Finish: 11-10-03

Dur: 7,5 days

Res:    

Facade

Start:  11-09-19

ID:   90

Finish: 11-09-27

Dur: 7 days

Comp: 0%

Horizontal thermal and acoustic insulation made of polystyrene , vertical insulation with mortar with metal lath

Start:  11-09-19

ID:   91

Finish: 11-09-22

Dur: 4 days

Res:    

Gypsum plaster of category II, external walls, mechanically made

Start:  11-09-23

ID:   92

Finish: 11-09-27

Dur: 3 days

Res:    

Internal plasters

Start:  11-10-04

ID:   96

Finish: 11-10-10

Dur: 5 days

Comp: 0%

Common plasters, mechanically made, walls, category II, buildings up to 8 floors

Start:  11-10-04

ID:   97

Finish: 11-10-07

Dur: 4 days

Res:    

Common plasters, mechanically made, slabs , category II, buildings up to 8 floors

Start:  11-10-04

ID:   98

Finish: 11-10-10

Dur: 5 days

Res:    

Flooring

Start:  11-10-11

ID:   99

Finish: 11-10-19

Dur: 6,5 days

Comp: 0%

Leveling layers under flooring , made of cement mortar with thickness 20 mm, trowelled

Start:  11-10-11

ID:   100

Finish: 11-10-19

Dur: 6,5 days

Res:    

Wood flooring

Start:  11-10-11

ID:   101

Finish: 11-10-18

Dur: 5,5 days

Res:    

Lacquering of flooring and parquets

Start:  11-10-11

ID:   102

Page 14

background image

Stairs railing made of steel bars

Start:  11-09-15

ID:   94

Finish: 11-09-15

Dur: 0,5 days

Res:    

Balcony railing with steel handrail 

Start:  11-09-15

ID:   95

Finish: 11-09-15

Dur: 1 day

Res:    

Finish: 11-10-12

Dur: 2 days

Res:    

Flooring made of articial stones, preparing the base

Start:  11-10-11

ID:   103

Finish: 11-10-11

Dur: 0,5 days

Res:    

Flooring made of articial stones, plates 15x15 cm, common method

Start:  11-10-11

ID:   104

Finish: 11-10-14

Dur: 3,5 days

Res:    

Page 15

background image

Critical

Noncritical

Critical Milestone

Milestone

Critical Summary

Summary

Critical Inserted

Inserted

Critical Marked

Marked

Critical External

External

Project Summary

Highlighted Critical

Highlighted Noncritical

Page 16

Project: Project1
Date: Fri 11-05-27