MRP PREREQUISITES 

 

 

 

  Requirements planning for the corresponding plant must be activated in 

Customizing for Materials Management under Consumption-Based Planning 

→ 

Planning 

→ 

Activate Material Requirements Planning

 

   The plant parameters for the corresponding plant must be activated in 

Customizing for Materials Management under Consumption-Based Planning 

→ 

Plant Parameters

→ 

Carry Out Overall Maintenance of Plant Parameters

 

  In  the  material  master  record,  you  have  to  maintain  the  MRP  data  of  the 

materials that are subject to automatic planning. 
 

  Automatically  planned  materials  are  not  assigned  with  MRP  type  ND  (=  not 

planned). 

 

 

 

background image

MRP RUN 

During the MRP Run the system will check the Planning file entry exist for the material or not, If 

 

 

 

 

Yes 

 

No 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

    MRP Type 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   Lot Size 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   Scheduling 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

    External Procurement (PR to PO)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Whether 
to Order 

How 
much to 
Order 

How to 
Order 

When to 
Order 

Internal Procurement 
(Planned order to Order) 

Re Order point planning 

Forecast based planning 

Time Phased planning 

Optimizing 

Periodic 

Static 

Replenish to max 

Fixed Lot 

Lot for Lot 

Planned order to PR 
conversion 

GR Processing Time - FC 

Planned Delivery Time- NC 

Purchasing Processing Time - FC