background image

CSM CUTTER SOIL MIXING - A NEW TECHNIQUE FOR THE 

CONSTRUCTION OF SUBTERRANEAN WALLS 

INITIAL EXPERIENCES GAINED ON COMPLETED PROJECTS 

E. Stoetzer, F.-W. Gerressen, M. Schoepf, BAUER Maschinen, Schrobenhausen, Germany

 

 
 
 
 

 

 

Introduction 

Bauer Maschinen GmbH developed the CSM 
technique in 2003 by drawing on the 
experience gained in the production and 
deployment of diaphragm wall cutters in the 
construction of cut-off and diaphragm retaining 
walls. 

The CSM System differs essentially from 
traditional techniques, in which the existing soil 
is mixed in-situ with self-hardening slurry by 
mixing tools rotating about a vertical axis, by 
using a mixing tool that rotates about a 
horizontal axis. 

Construction principle 

The soil is mixed with self-hardening slurry, 
which is simultaneously introduced into the soil 
mass, to produce a wall construction material 
that takes on the role of a cut-off or structural 
retaining wall. 

The following construction sequence is 
generally adopted: 

a) Construction of a good sized open guide 
trench for retaining excess slurry.  

b) Fluidization of the soil mass during 
penetration to the terminal depth as an 
appropriate slurry is simultaneously 

introduced. Depending on the prevailing 
conditions, either bentonite slurry is added to 
the mixing and fluidization process or cement 
slurry is introduced into the soil during 
penetration. The volume of slurry injected is 
determined by the rate of cutter penetration. 

c) During withdrawal, the precise volume of 
slurry required for producing the final wall 
construction material is injected. 

d) A continuous wall is formed by the 
construction of individual panels in an 
alternating sequence of overlapping primary 
and secondary panels. Secondary panels can 
be constructed immediately after completion of 
primary panels, i.e. „soft-into-soft“. The cutter 
technology does, however, also enable cutting 
into panels that have already hardened, i.e. 
„soft-into-hard". 

e) To utilize the wall as a structural retaining 
wall, steel columns (IPB sections) are inserted 
into the freshly mixed wall panels. 

Plant and equipment 

The size of individual panels is determined by 
the type and size of equipment being 
deployed. Panels can be constructed in 
lengths ranging from 2.2 m to 2.8 m and wall 
thicknesses of 0.5 m to 1.0 m. 

In all known soil mixing processes the existing soil is mixed with self 
hardening slurry by mixing tools that rotate about a vertical axis (augers, 
mixing paddles). Wall panels are constructed using sets of triple mixing 
tools combined into a single unit. These techniques have been developed 
on the principle of the rotary drilling technology. In contrast, the new Cutter 
Soil Mixing or CSM technique is derived from the cutter technology. 
The soil is loosened and broken down by cutter wheels then mixed in-situ 
by the rotating cutter wheels with the self-hardening slurry - introduced into 
the ground between the two wheels - to form a soil-slurry mortar. The main 
area of application lies in the construction of cut-off and retaining walls.  

background image

Fig. 1 Mixing wheels and housing for 
          hydraulic  gear drives 

The most important elements of the CSM unit 
are the cutter gear drives. They are driven by 
hydraulic motors which are located in a water-
tight housing. 

Fig. 2 Types of wheels 

For loosening and mixing the soil different 
types of mixing wheels were developed. 
Selection of the correct wheel and set of teeth 
is the main pre-condition for cost-effective 
operation, minimal wear and for obtaining a 
homogeneous soil-slurry mixture.  

The slurry is introduced into the soil directly 
between the mixing wheels. During 
construction, the counter-rotating mixing 
wheels and vertically mounted plates are 
effectively acting like a forced action mixer. 

The mixing unit is either mounted on a guided 
Kelly bar or on a wire rope-suspended cutter 
frame equipped with special steering devices. 

The standard set-up is the "Kelly-guided" 
variant capable of reaching depths up to 35 m. 

"Rope-suspended" systems are particularly 
suited for construction of deep soil mix walls. 
The greatest depth at which a wire rope-
suspended unit has successfully installed a 
soil mix wall to date is 55 m. 

Fig. 3 Kelly-guided CSM unit (Japan) 

Fig. 4 Wire rope-suspended frame-mounted 
          CSM unit (Germany) 

background image

Both systems must be accompanied by an 
intensive quality assurance programme. All 
process-specific production and plant-specific 
operating data are visualised throughout the 
construction phase and stored for subsequent 
documentation and evaluation.  

Fig. 5 Rig operator’s on-board computer 
          screen  

Comparison with other techniques 

The CSM process has significant advantages 
over conventional techniques: 

The existing soil is utilised as construction 
material. 

Very little spoil material is generated; this 
renders the technique particularly suited for 
work on contaminated sites. 

CSM is an ideal alternative to the "Berlin" 
retention wall system in high groundwater 
conditions, or to sheet pile walls in soil 
formations unsuitable for pile driving or in 
close proximity to vibration-sensitive buildings. 

Wall depths of 25 m and daily production rates 
of 200 m² can be achieved with relatively light 
base machines of 70 – 90 tones total 
operating weight and installed power outputs 
of 260 – 300 kW. 

A high degree of verticality of wall panels is 
achieved by the counter-rotating cutter wheels. 

The cutter principle ensures construction of 
clean and trouble-free joints even between 
wall panels of different construction age e.g. 
after weekend breaks or prolonged stoppages 
on site. 

Harder soil formations can be easily 
penetrated, broken down and mixed by using 
the cutter wheels as cutting and mixing tool. 

First results 

Between December 2003 and January 2004, 
feasibility tests were carried out at the BAUER 
Maschinen test site in Aresing with the aim to 
construct watertight retaining walls to depths 
of up to 20 m using a new soil-mixing process.  
The soil at the test site consists essentially of 
a 6 m thick layer of gravelly sand and an 
underlying mass of fine sands and silts. The 
ground-water level stands at approx. 3 m 
below ground level. 

The feasibility tests were carried out in co-
operation with the specialist foundation 
contractor Soletanche-Bachy of France. 

To develop the technique into a construction 
process for full scale production, a quasi 
circular wall in the shape of polygon was 
constructed with a diameter of 8 m and a 
depth of 20 m. The loads imposed by both 
earth and hydrostatic pressure are carried 
through the circular vault effect. Neither 
reinforcement nor steel sections were inserted 
into the wall. The shaft was excavated to a 
depth of 10 m. All wall panels and joints are 
watertight. Compressive strengths of 6-10 
MPa were attained. 

Fig. 6 Test site Aresing CSM rig and  
          completed shaft 

The CSM system was showcased at BAUMA 
2004 in Munich, Germany, where it received 
the "Innovation Price of the German 
Construction Machinery Day 2004" 
(Innovationspreis des Deutschen Bau-
maschinentages 2004). At BAUMA 2004, the 
system was immediately taken up by a 
Japanese client, who subsequently carried out 
a series of feasibility tests with the technical 
support of BAUER Maschinen to examine 

background image

possible applications under Japanese 
conditions.  

The soil conditions in which these tests were 
carried out were typical for Greater Tokyo: 

a 7 m thick very soft clay layer underlain by 
loose (interbedded layers of medium dense) 
silty fully saturated fine sands. 

The work was carried out based on criteria 
commonly applied in Japan (mix with a high 
w/c ratio, high pump volumes with high 
proportion of return flow). The results show 
that the requirements were clearly satisfied: 

High soil mixing outputs were achieved (up to 
40 m³/h). 

Steel sections were inserted without difficulty 
to the design depth of 15 m.  

The clay layer resulted in a much more 
homogenous mix when compared with other 
techniques commonly used in Japan.

 

Fig. 7 Soil-cement slurry whirled up by the 
         addition of air during penetration phase 

Completed projects 

After the initial experience gained in 2004, a 
total of 25 projects were carried out world-wide 
in 2005. 

The projects were concentrated in the Benelux 
countries (Fig 8), Italy and the classic soil mix 
country, Japan. Here, the most diverse 
applications were found for the CSM process, 
whereby the clients of Bauer Maschinen 
GmbH showed also a high degree of creativity. 

 

Fig. 8 Retaining wall constructed by 
          the CSM process (The Netherlands) 

Besides the classic application of the 
technique as retaining and cut-off wall, CSM 
panels were also deployed as foundation 
elements. A further test was to show, whether 
soils, which are unsuitable for vibratory pile 
driving techniques, can be treated in-situ by 
the CSM system to facilitate subsequent 
driving of sheet piles. The wire rope-
suspended CSM unit provided positive results 
for soil mixing at depths of up to 55 m. 

CSM as foundation elements 

On several building projects CSM panels were 
used as foundation elements. Apart from the 
main advantages of the CSM process, such as 
the use of the existing subsoil as construction 
material and the minimized spoil removal, a 
further advantage results from the fact that the 
same equipment can be deployed to construct 
first the retaining wall for the excavation and 
then the foundation elements. 

Fig. 9 Wall panels with integrated foundation 
          elements 

background image

To date, the technique has been used in 
different variations. On one of the projects, for 
example, foundation elements were 
constructed concurrently with the retaining wall 
and connected with each other in such a way 
that the retaining wall was subsequently also 
capable of carrying vertical loads. (Fig. 9)  

On another project, CSM panels reinforced 
with tension bars were used as uplift anchors 
to tie-down a raft foundation in adverse 
groundwater conditions. 

Fig 10 CSM wall and CSM panels reinforced 
           with tension bars used as uplift anchors 

CSM as ground treatment technique 

As part of a proposed scheme to prevent 
contaminants escaping from a refinery in 
Sicily

,

 a sheet pile wall was to be installed to a 

depth of 18 m. Construction of the seepage 
prevention scheme by way of conventional 
cut-off techniques was not possible, as the 
highly contaminated subsoil could not be 
removed off site.  

The ground conditions were not suitable, 
however, for conventional sheet pile wall 
installation: 

0 - 5m   

sandy fill (made ground) 

5m - 10m 

cemented sands 

below 10 m 

clay 

The cemented sand layers proved to be a 
significant obstacle to pile driving. The largely 
weathered formation was interbedded with 
non-weathered bands with unconfined 
compressive strength values of up to 40 MPa.  

The task of the CSM process was to prepare 
the soil to the top of the clay layer in-situ so 
that (a) excavation of the soil would be 
avoided, and (b) subsequent installation of the 
sheet pile wall would be assured.  

Deep CSM panels 

After a series of trials in Germany and Japan 
using the wire rope-suspended CSM method 
for greater depths, a shaft was constructed for 
the Quality Assurance Department of Bauer 
Maschinen. The shaft is to provide a facility for 
testing Kelly bars from our own production line 
under site conditions. For this purpose, four 
CSM panels were constructed to a depth of 55 
m to form a rectangular shaft, the inside of 
which was subsequently drilled out to a depth 
of 50 m. 

Fig.11 Excavated shaft (depth 55 m) 
            supported by four CSM panels 

Construction of the shaft was carried out by 
the two-stage technique. During penetration of 
the mixing tool the soil is fluidized and mixed 
with bentonite slurry (Fig. 12). 

During withdrawal of the mixing tool the final 
wall construction material is product by the 
introduction of cement slurry (Fig. 13). 

background image

Fig. 12 Fluid soil-bentonite backflow 

Fig. 13 Finished panel (overflow soil-cement)  

 

The main advantage of the two-stage 
construction technique is the fact that 
production of a panel can be interrupted during 
penetration without any problem, i.e. for a shift 
change, and subsequently be resumed by re-
entering the pre-mixed trench. Only after 
having reached the terminal depth and 
switched to cement slurry the completion of 
the panel in a single operation is 
advisable.Treatment of the discharged soil-
bentonite mud is facilitated by the additional 
deployment of a mud regeneration plant. The 
cleaned bentonite can be re-cycled for reuse 
and the extracted soil particles can be 
removed off site.  

Conclusions and future outlook 

The above examples have demonstrated that 
a new construction technique, which combines 
the advantages of the cutter and soil mixing 
technology has been successfully established 
in the market. The technique offers a great 
diversity of possible applications, such as cut-
off walls, structural retaining walls foundation 
elements and numerous others.  

The capacity to reach great depths offers an 
enormous potential for the construction of 
deep cut-off walls for dams or the en-
capsulation of contaminated sites.