background image

C

H

A

P

T

E

R

12

P

LANNING THE

I

NSTALLATION

T H O M A S   A.   D O O L E Y   A N D  

J E R A L D   R.   R O U N D S

THE PROCESS OF PLANNING

Planning is one of the most important parts of any project and is particularly crit-
ical  in  construction.  One  of  the  characteristics  of  construction  is  that  it  is  not
repetitive. Although specific activities such as pulling cable or making termina-
tions  appear  to  be  repetitive,  each  is  done  under  different  circumstances.  The
cumulative result of these small differences is that jobs differ considerably. As a
result, each job must be planned in detail to take its unique characteristics into
consideration.

In  manufacturing,  prototypes  are  designed  and  manufactured  to  test  the

design and the manufacturing procedures. When mistakes and oversights occur,
another  prototype  is  developed  to  solve  the  problems.  This  process  is  repeated
many times over until both the product and the process of making that product
are flawless, at which time the product goes into production.

In  the  construction  industry,  you  do  not  have  that  luxury.  Designers  must

design correctly the first time. Constructors must build right the first time. Errors,
either  in  design  or  construction,  are  costly  to  repair  or  replace  and  cause  time
delays.  Some  errors  are  hidden  and  do  not  become  obvious  until  the  system  is
operating. Then, the mistakes become not only costly and time-consuming, but

129

background image

are disastrous to those who depend on a fully operational and properly working
system.

The only way to produce a quality job is to avoid errors, omissions, and mis-

takes by properly planning and by establishing correct installation procedures. A
side benefit of the planning process, of course, is that it improves the efficiency of
installation, which results in higher profits for a contractor. Preplanning of every
aspect of fiber optic installation is not an option; it is a necessity.

MEASURING FOR CONDUIT PULLS

Planning for proper cable lengths is extremely important in fiber optic installa-
tion for two reasons. The most important is that splices cause loss in both signal
quality  and  strength—this  should  be  avoided.  In  fact,  most  designers  specify
point-to-point  or  device-to-device  runs  to  avoid  needless  signal  loss  due  to
splices. The second reason, especially important to the contractor, is that splices
cost time and money.

Measurements must be taken by an experienced field hand who understands

the importance of correct and accurate measurements. Often, this is done by the
project engineer or the job site superintendent.

There are three ways to measure the path to be used for the fiber. They are

listed from least to most desirable.

1. Measurements taken from the set of prints. This works if you want to

invest in a great deal of extra material. The objective of design drawings
is to show generally where runs are supposed to be located. However, it
is virtually impossible for the designer to anticipate all field conditions,
and it is not the designer’s intent to do so. Thus, taking accurate mea-
surements from the design drawings is not possible and results in runs
that are, at best, marginally long or short. Long pieces of fiber must be
recut and short pieces are wasted.

2. Field  measurements  taken  with  a  wheel.  A  site  visit  with  a  measuring

wheel  and  a  set  of  drawings  will  yield  much  better  accuracy.  Certain
characteristics of the job site are given perspective with a field visit that
are not obvious from inspection of the drawings alone. During the site
visit, the drawings can be verified for accuracy, installation details such
as  pulling  locations  can  be  noted,  changes  such  as  variations  in  align-
ment or elevation can be identified, obstacles that might hinder the pull
can be discovered, and termination locations can be recorded.

3. Measuring  with  measurement/pull  tape.  By  far  the  most  accurate  and

efficient method of measurement is with measurement/pull tape (some-
times called mule tape). This is a flat ribbon, consecutively numbered in
feet, that is usually made with polyester or aramid yarn and sometimes

130

CHAPTER 12 — PLANNING THE INSTALLATION

background image

coated with plastic for waterproofing. It comes in different lengths and
pull strengths.

Completing  the  measurement  process  requires  adding  extra  length  for

splices,  terminations,  and  future  access  coils,  if  specified.  The  amount  of  addi-
tional cable needed for splicing depends on site conditions, splicing method used,
and long range plans for cable usage. Termination needs only about 7 to 10 feet
of  additional  cable  beyond  the  place  the  terminal  will  be  mounted.  Access  or
repair coils generally range in length from 30 to 50 feet per span. A good guide-
line is to allow 1 percent extra for outside plant cable and 5 to 7 percent extra for
inside cable.

SPLICING

Fusion  splicing  cannot  be  done  in  explosive  environments  such  as  manholes.
Therefore, each end coming into the splice that will finally end up in the manhole
will have to have enough length to reach a tent or van near the manhole where
the splice will actually be made. Usually, about 30 feet of extra length should be
added for each side of the splice—resulting in additional 60 feet of cable.

Mechanical splicing can be done inside manholes. Mechanical splices require

only about 10 feet of overlap, instead of the 60 feet for a fusion splice. Remember
that these measurements are in addition to whatever length will be required to
properly rack the cable within the manhole.

TERMINATIONS

When terminating fiber, it is important to place the terminal in a safe, noncon-
gested area. If the end user has no preferences, place the terminal as close as pos-
sible to the fiber optic transmission equipment. It is most important to protect the
exposed fibers, so choice of a termination location must consider a working envi-
ronment that allows adequate working space.

EFFICIENT PULLING

When installers first become involved in fiber optic installations, they can easily
become overconfident about how much cable length can be successfully pulled at
one  time.  This  is  probably  because  of  the  small  size  and  weight  of  fiber  optic
cable. It is better to divide a pull in half, or even thirds, usually at corners or pull
boxes, than to fail in pulling a long run.

A pulling operation must be discontinued when the pulling tension reaches

the cable limit. The discontinued pull will have to be aborted, the cable pulled
back out and replaced on the reel, and the pull started again, either with shorter

CHAPTER 12 — PLANNING THE INSTALLATION

131

background image

runs or better lubrication or both. The cable may be reused if the pull or extrac-
tion has not damaged it.

Every  effort  must  be  made  to  plan  the  pull  so  that  pulling  locations  have

plenty of work space. The knowledgeable designer will designate several appro-
priate  locations  for  breaking  up  the  pull.  The  installer  must  ensure  that  if  the
designer has not indicated where multiple pulls are necessary, he or she can deter-
mine  appropriate  locations  for  intermediate  pulls  before  work  is  begun  in  the
field. It is better to tie up one lead technician before the pulling starts than the
whole crew after it has begun.

Most point-to-point pulls can be accomplished by crews of two or three peo-

ple. One person pays the cable off the reel and into the duct in order to reduce tail
load (the term used to designate that force required to get cable off the reel and
into the duct). One or two people pull at the other end. The size of crew is deter-
mined by considerations such as:

Length of pull
Total degrees of bend
Tail loading
Use of lubricant
Use of power pulling equipment

When planning to start a pull, the installer must make sure there is enough

time to finish the job the same day. It is unwise to leave half a reel of cable, worth
anywhere from $5,000 to $375,000, lying around in unsecured areas. If a reel
must be left exposed to the public, strong consideration should be given to assign-
ing a security guard to watch over the reel. An occasional investment of $75 or
$100 to avoid theft of an expensive reel of cable, to say nothing of the distur-
bance to the job if the cable is gone when installers arrive to begin work in the
morning, is a wise investment

Exact  terminating  locations  must  be  identified  in  advance.  This  obvious

though often overlooked step can lead to costly mistakes if forgotten. The cable
must be pulled all the way to where it will be terminated, not just into the room.
The designer should provide a fold-flat diagram (which results from folding out
the walls of the room as if they were the sides of a box hinged at the intersections
of the walls and the floor) for each terminating room as a part of the initial plan-
ning walkout.

ADEQUATE DUCT SPACE

Current industry practice, outside telephony, tends not to utilize available duct
space very efficiently. As a result, one often finds a 1/2-inch fiber cable as the only
cable  in  a  4-inch  duct.  As  a  matter  of  good  design,  cable  should  fill  approxi-
mately 60 to 70 percent of the available duct space.

132

CHAPTER 12 — PLANNING THE INSTALLATION

background image

Since it is difficult to pull cable into a duct that is already occupied, it is very

important to detail, on the print, where the different media will be pulled. Since
most fiber cables are 3/4-inch or smaller in diameter, for efficient use, the larger
3- or 4-inch diameter conduits should be subdivided with innerducts.

Innerduct is flexible, nonmetallic conduit that is pulled in multiples into the

main  conduit.  It  is  made  of  polyethylene  and  comes  with  a  pull  rope  already
installed within it. Innerduct serves a threefold purpose:

Subdividing the main duct
Protecting the fiber cable
Reducing friction

The inside of the innerduct is designed to let the cable glide smoothly within

it. This is accomplished by the use of special coatings and by the physical proper-
ties of the inner wall. Corrugated innerduct is the most popular form because of
its  flexibility.  A  3-inch  conduit  can  be  subdivided  with  up  to  four  1-inch
innerducts; up to six 1-inch innerducts can be placed in a 4-inch conduit.

Innerduct not only allows the initial fiber installation to be effectively accom-

plished, but allows expansion capabilities to be built into the system. This can
provide great return on investment if there is any expectation of future expansion
of the fiber system.

INITIAL PLANNING WALKOUT

Prior to the start of cable pulling, a planning walkout should be performed by the
project engineer, the lead technician, and the project superintendent. The project
engineer,  responsible  for  system  design,  will  be  well  aware  of  the  customer’s
needs. The lead technician, an experienced fiber installer who will not necessarily
be  the  one  who  will  do  the  installation,  has  the  responsibility  to  plan  and  to
answer as many questions as possible before the crew is on site. The superinten-
dent can provide general project information and needs to know as much as pos-
sible about the installer’s activities to coordinate with other trades and activities
in the vicinity of the installation.

The walkout should start at one termination site (Figure 12-1). This location

will  be  designated  with  a  clearly  stated  name,  such  as  “#12  Communication
Room.”  A  rough  fold-flat  sketch  will  identify  the  fiber  terminal  location  and
locations of other major system components, as well as other relevant features in
the room. The floor and walls will be marked with a pencil to indicate approxi-
mate locations of terminations. Notes should be made on the sketch concerning
conduit type and size, as well as whether pull string or measurement/pull tape has
been used. Verification of whether multiple ducts are involved is requested from
the superintendent.

CHAPTER 12 — PLANNING THE INSTALLATION

133

background image

Figure 12-1

Preplanning walkout sketch.

Identification  should  be  made  defining  which  conduits  go  where  either  by

visual inspection or by tugging on the pull tape. The path of the conduit should
then  be  walked,  making  note  on  the  diagram  of  any  pull  boxes,  manholes,  or
other abnormalities. This process must be carried out for each run on the job.

The  more  information  the  engineer  provides  on  the  print,  the  faster  the

installation  will  progress.  Remember,  the  object  of  this  planning  walkout  is  to
prevent the entire pulling crew from being idle while the lead technician tries to
track down the engineer or superintendent for clarifications or additional infor-
mation.

REVIEW QUESTIONS

1. The most accurate method of measuring for conduit pulls is ___________

a. from a set of prints.

b. field measurements taken with a wheel.

c. measuring with a pull tape.

134

CHAPTER 12 — PLANNING THE INSTALLATION

1

2

3

4

5

1 Room Location for Terminations
2 Bends
3 Conduit Size
4 Manholes
5 Pull Locations

background image

2. How much extra cable must be added to make a fusion splice in a man-

hole?

a. 30 feet

b. 1 percent

c. 30 feet for each side of the splice

d. 10 feet

3. Subdividing larger conduits with innerducts _____________

a. efficiently uses duct space.

b. allows for future expansion.

c. offers additional protection to the fiber optic cable.

d. all of the above

4. The purpose of a planning walkout is to _____________

a. get a rough idea of the installation.

b. measure the conduit run.

c. clarify all the final details.

d. none of the above

CHAPTER 12 — PLANNING THE INSTALLATION

135

background image