background image

1

PGE Górnictwo i Energetyka Konwencjonalna S.A.

3rd March,   2011

CCS Demonstration Plant fully 

integrated into new unit 858 MW

background image

2

Technical specification  

of CCS Installation (Basis for Design)

The

Bełchatów CCS Project will include the following key

components:

Power Plant with gross electrical output 858 MWe
Carbon Capture Plant & Integration: an integrated post-
combustion Carbon Capture Plant (CCP) with an installed size of
260MWe gross electricity output. The CCP utilizes an Advanced
Amine Process technology with a CO2 capture efficiency of at least
85%. This component will also include the modifications necessary
to the base installation, i.e. Power Plant, to make it capture ready.
CO2 Transportation: this component will include a pipeline and
an associated infrastructure to transport the CO2 captured and
compressed by the CCP to the storage site.
CO2 Storage: this includes the injection of pressurized CO2 into
a deep saline aquifer for permanent storage

background image

3

Major elements of complexity of the CCS 

Project

The new 858 MWe power generation unit which is under last phase 
of the construction was originally not designed to be ‘CO2 Capture 
Ready’. This means that some modifications to the installation will 
have to be implemented to ensure an integration of the CCP. The 
key modifications include:

Re-engineering and re-location of equipment from areas 
identified for the CCP.
qTie-in for off-take and return of cooling water required for the 
CCP.
qTie-in for off-take and return of flue gas to the main flue gas 
ducts.
qModification of IP/LP turbine crossover pipes.
qControl tie-in.

background image

4

CCS value chain

Scenario 1: vertical wells

Flow lines

Storage

I1

I2

I3

I4

M1

Manifold

Scenario 2: horizontal wells

Vertical Wells (Scenario 1)

Horizontal wells (Scenario 2)

M1

Entry of main storage Manifold

I1

Injector well 1

Injector well 1

I2

Injector well 2

I3

Injector well 3

I4

Injector well 4 (if applicable)

Injector well 4 

Flow lines

Storage

I1

M1

Manifold

I4

Pipeline

Pipeline

background image

5

CCS Project Programme

Capture installation

Building permit validation: 22 Feb  2010 - completed
qCompletion of Capture Ready modifications: October 2010  completed
qMechanical completion: May 2014

Transport

q

EIA study:  Aug 2012

qBuilding permit: July 2014
qConstruction completion: April 2015

Storage

qStorage site selection: June 2011
qSite characterization: Jan 2014
Surface Facilities construction completion: July  2015 
National Injection permit: Sept  2015

Optimization process completion and CCS final acceptance - Dec 

2015

background image

6

Current critical tasks

Geological work of phase I completion and storage site selection 

by the end of I half of 2011 

2 Gravimetric pictures - ~1000 km2/ per structure

Seismic survey - ~500 km length of 2D seismic profiles

2 appraisal wells, drilling tests, cores examination

Modeling, seismic inversion,  injection scenarios, risk assessment, site ranking 

using all criteria – 3 structures

Completion of capture FEED study for capture

Early work programme for capture – detail engineering for key 

equipment

Setting forth procedures for  further evaluation of  CCS 

components

Public awareness campaign 

background image

CCP 3 D visualisation

background image

Status of storage component - I phase 

Site selection was originally scheduled for the end of 2010. Currently it is

anticipated to be completed by the end of first-half of 2011. The reasons
for this delay are
:

q public procurements rules implicated in

longer the tender

proceeding on geology work contractors selection (protests, ex
ante control)

q problems with public acceptance - large numbers of protests

expressed by communes authority representatives amplified by
environmental NGO’s with reference to

the geology and

geophysical field work

q eventually work programme was done, currently gathered data

are

under

processing/interpretation/modelling

by

Polish

Geological Institute/SLB

8

background image

9

CCS  Project Contracors

Capture island

q Alstom Group – Partner in development of „advanced amine” technology

q Dow Chemical – Supplier of selected solvent to capture CO

2

from industrial flue

gas stream

Integration – „Capture ready”

q Alstom Group

Transport

q Gazoprojekt – Feasibility Study
q Contractor for engineering and construction – to be selected

Geology

q Polish Geological Institute (PIG) and Schlumberger – Support during first

appraisal phase

q Additional subcontractors – PBG Ltd, Geofizyka

Toruń, Sp z o.o., PRWiG

PGE Mining and Conventional Power JSC

background image

10

CCS Project risks

q

Technology is not commercially available yet, risk of scaling up 

from pilot to industrial level, constantly exists

Necessity of optimal project financial structure concept
Power net efficiency reduction caused by CO

2

capture process

Possibility of lack on public acceptance for CCS, and particularly 

concerning CO

2

transport and geological storage additionally 

amplified by some local environmental NGO’s

q

Risk of unobtaining during II phase storage component realisation   

to confirm possibilty of permanent and   safe geological CO

2

storage within selected geological structure 

background image

11

CCS financial structure

Non - returnable:

EEPR –

180 mln EUR

– Grant Agreement signed with EC, May

5th, 2010.

Financing Sources Under Consideration

NER 300
Norwegian Financing Mechanism
European Investment Bank European Bank for Reconstruction 

and Development 

Own equity

background image

External public engagement campaign according 

to phase I - site selection

background image

13

Thank you for your attention

Marzena Gurgul

CCS Project Director

"The sole responsibility of this publication lies with the author. 

The European Union is not responsible for any use that may be made of the information contained 

therein."


Document Outline